Installation Status
- Collimation Production Meeting Minutes 2014
- Collimation Production Meeting Minutes 2013
- Installation Planning LS1 (from J.Coupard)
- Pictures DFS Collimation Maintenance
ALL Collimators Completed 2014-07-14
Collimators without BPMs: next for installation 2 TCL6s in IP5 Completed 2014-07-14
Collimators with BPMs (external production) Completed 2014-07-10
TCL4 IP1 and IP5 (CERCA)
Installation | HW Id. and MTF link | Link | Comments |
---|---|---|---|
10/09/2013 | HCTCLP_001-CQ000408 | Installed as TCL-4 in TCL.4L1.B2 | |
10/09/2013 | HCTCLP_001-CQ000410 | Installed as TCL-4 in TCL.4R1.B1 | |
12/11/2013 | HCTCLP_001-CQ000406 | (TCTVA.4L2.B1) to be installed as TCL-4 in TCL.4R5.B1 | |
12/11/2013 | HCTCLP_001-CQ000407 | (TCTVA.4R2.B2) to be installed as TCL-4 in TCL.4L5.B2. Switch stop replaced. |
TCL6 IP1 and IP5 (CERCA)
Installation | HW Id. and MTF link | Link | Comments |
---|---|---|---|
03/06/2014 | HCTCT__001-CQ000308 | (TCTH.4R1.B2) installed as TCL-6 in TCL.6R1.B1 | |
03/06/2014 | HCTCT__001-CQ000307 | (TCTH.4L1.B1) installed as TCL-6 in TCL.6L1.B2 | |
HCTCT__001-CQ000301 | (TCTH.4R5.B2) installed as TCL-6 in TCL.6R5.B1 | ||
10/07/2014 | HCTCT__001-CQ000305 | (TCTH.4L5.B1) installed as TCL-6 in TCL.6L5.B2 |
TCP IP7 (CERCA)
Installation | HW Id. and MTF link | Link | Comments |
---|---|---|---|
10/03/2014 | HCTCP__001-CQ000104 | TCP.D6L7.B1 No baked-out | |
10/03/2014 | HCTCP__001-CQ000108 | TCP.C6L7.B1 No baked-out | |
10/03/2014 | HCTCP__001-CQ000102 | TCP.B6L7.B1: TCP_107 - TCP_102 Baked-out | |
17/02/2014 | HCTCP__001-CQ000111 | TCP.D6R7.B2 Baked-out because there was some vacuum work |
NEW collimator design, TCSP (CERN)
Installation | Slot | HW Id. and MTF link | Link | Comments |
---|---|---|---|---|
14/02/2014 | TCSP.A4R6.B1 | HCTCSP0001-CR000001 | TCSP-Secondary Collimator with Pick-up | |
spare | -- | HCTCSP0001-CR000002 | TCSP-Secondary Collimator with Pick-up | |
10/03/2014 | TCSP.A4L6.B2 | HCTCSP0001-CR000003 | TCSP-Secondary Collimator with Pick-up | |
NEW collimator design, TCTP (CINEL)
Installed | Slot | HW Id. MTF link | Link | Comments |
---|---|---|---|---|
05/03/2014 | TCTPH.4R1.B2 | HCTCTP0001-CZ000001 | Skipped bake-out at CINEL | |
05/03/2014 | TCTPV.4R1.B2 | HCTCTP0001-CZ000002 | Skipped bake-out at CINEL | |
14/04/2014 | TCTPH.4L1.B1 | HCTCTP0001-CZ000003 | High torque at CINEL | |
14/04/2014 | TCTPV.4L1.B1 | HCTCTP0001-CZ000004 | ||
15/04/2014 | TCTPH.4R8.B2 | HCTCTP0001-CZ000005 | To Be Replaced | |
17/04/2014 | TCTPV.4R8.B2 | HCTCTP0001-CZ000006 | ||
22/05/2014 | TCTPV.4R2.B2 | HCTCTP0001-CZ000007 | ||
22/05/2014 | TCTPH.4R2.B2 | HCTCTP0001-CZ000008 | ||
23/05/2014 | TCTPH.4L2.B1 | HCTCTP0001-CZ000009 | RF finger for BD jaw repaired | |
23/05/2014 | TCTPV.4L2.B1 | HCTCTP0001-CZ000010 | ||
10/06/2014 | TCTPH.4R5.B2 | HCTCTP0001-CZ000011 | ||
10/06/2014 | TCTPV.4R5.B2 | HCTCTP0001-CZ000012 | ||
06/06/2014 | TCTPH.4L8.B1 | HCTCTP0001-CZ000013 | ||
06/06/2014 | TCTPV.4L8.B1 | HCTCTP0001-CZ000014 | ||
10/07/2014 | TCTPV.4L5.B1 | HCTCTP0001-CZ000015 | ||
10/07/2014 | TCTPH.4L5.B1 | HCTCTP0001-CZ000016 | ||
20/01/2015 | TCTPH.4R8.B2 | HCTCTP0001-CZ000019 | ||
spare | HCTCTP0001-CZ000017 | MTF | EDMs | TCTP-Tertiary Collimator with Pick-Up. Vacuum leak found during qualification tests. |
spare | HCTCTP0001-CZ000018 | MTF | EDMs | TCTP-Tertiary Collimator with Pick-Up |
spare | HCTCTP0001-CZ000020 | MTF | EDMs | TCTP-Tertiary Collimator with Pick-Up |