Collimators with embedded BPMs
Description
16 TCT-tungsten collimators and 2 TCSG-CFC collimators will be replaced by collimators with embebed BPM buttons during LS1.
EN/MME will provide EN/STI with 3 TCSP collimators (2 + 1 spare) inside a welded tank (same deliverable as CERCA during Phase I production); STI to prepare collimators for installation.
The TCTs will be produced by CINEL.
Pictures

Final TCTP naming and positions

References
- A.Dallocchio @ CWG, 24th June, 2013, Status of production of TCS with BPMs
- C.Boccard @ CWG, 8th July, 2013, Antenna test procedures on BPM collimators
- C.Boccard @ EDMS Id 1169909: Electrical tests BPMs
- G.Bregliozzi @ CWG, 8th July, 2013, Outgassing: TCTP acceptance limits
- EDMS No. 1304880, LHC collimators embedding beam BPMs (TCTP and TCSP)
Status
The equipment codes for the tables for CECOM and the collimators (TCTP for Cinel and TCSP for CERN) are created.
Assembly Id. | Link | Link | Comments | |
---|---|---|---|---|
CERN | HCTCSP0001-CR000001 | MTF | EDMS | TCSP-Secondary Collimator with Pick-up |
CERN | HCTCSP0001-CR000002 | MTF | EDMs | TCSP-Secondary Collimator with Pick-up |
CERN | HCTCSP0001-CR000003 | MTF | EDMs | TCSP-Secondary Collimator with Pick-up |
CINEL | HCTCTP0001-CZ000001 | MTF | EDMs | TCTP-Tertiary Collimator with Pick-Up |
CINEL | HCTCTP0001-CZ000002 | MTF | EDMs | TCTP-Tertiary Collimator with Pick-Up |
CINEL | HCTCTP0001-CZ000003 | MTF | EDMs | TCTP-Tertiary Collimator with Pick-Up |
CINEL | HCTCTP0001-CZ000004 | MTF | EDMs | TCTP-Tertiary Collimator with Pick-Up |
CINEL | HCTCTP0001-CZ000005 | MTF | EDMs | TCTP-Tertiary Collimator with Pick-Up |
CINEL | HCTCTP0001-CZ000006 | MTF | EDMs | TCTP-Tertiary Collimator with Pick-Up |
CINEL | HCTCTP0001-CZ000007 | MTF | EDMs | TCTP-Tertiary Collimator with Pick-Up |
CINEL | HCTCTP0001-CZ000008 | MTF | EDMs | TCTP-Tertiary Collimator with Pick-Up |
CINEL | HCTCTP0001-CZ000009 | MTF | EDMs | TCTP-Tertiary Collimator with Pick-Up |
CINEL | HCTCTP0001-CZ000010 | MTF | EDMs | TCTP-Tertiary Collimator with Pick-Up |
CINEL | HCTCTP0001-CZ000011 | MTF | EDMs | TCTP-Tertiary Collimator with Pick-Up |
CINEL | HCTCTP0001-CZ000012 | MTF | EDMs | TCTP-Tertiary Collimator with Pick-Up |
CINEL | HCTCTP0001-CZ000013 | MTF | EDMs | TCTP-Tertiary Collimator with Pick-Up |
CINEL | HCTCTP0001-CZ000014 | MTF | EDMs | TCTP-Tertiary Collimator with Pick-Up |
CINEL | HCTCTP0001-CZ000015 | MTF | EDMs | TCTP-Tertiary Collimator with Pick-Up |
CINEL | HCTCTP0001-CZ000016 | MTF | EDMs | TCTP-Tertiary Collimator with Pick-Up |
CINEL | HCTCTP0001-CZ000017 | MTF | EDMs | TCTP-Tertiary Collimator with Pick-Up |
CINEL | HCTCTP0001-CZ000018 | MTF | EDMs | TCTP-Tertiary Collimator with Pick-Up |
CINEL | HCTCTP0001-CZ000019 | MTF | EDMs | TCTP-Tertiary Collimator with Pick-Up |
CINEL | HCTCTP0001-CZ000020 | MTF | EDMs | TCTP-Tertiary Collimator with Pick-Up |
Cad exchange folders, from CERN to CINEL