TCLD collimators

Description

One horizontal DS collimator (TCLD) with Inermet-180 jaws will be installed in cell 9 on each side of IR7 for cleaning the outgoing proton and heavy ion beams. To make space, a standard 8.33~T main dipole (MB) will be replaced by two shorter 11 T dipoles with the TCLD in between.

One TCLD collimator will also be installed on each side of IR2 in cell 11, at the location of the connection cryostat, without 11 T dipoles, for heavy-ions operation only.

Pictures

Layout DB functional positions

Name of the new collimatorColl. PlaneUpstream in-jaw BPMDownstream in-jaw BPMTank BPM
TCLD.11R2.B1HLHC.BPTUV.11R2.B1LHC.BPTDV.11R2.B1 LHC.BPTUH.11R2.B1
TCLD.11L2.B2HLHC.BPTUH.11L2.B2LHC.BPTDH.11L2.B2 LHC.BPTUV.11L2.B2
TCLD.9R7.B1HLHC.BPTUV.9R7.B1LHC.BPTDV.9R7.B1 LHC.BPTUH.9R7.B1
TCLD.9L7.B2HLHC.BPTUH.9L7.B2LHC.BPTDH.9L7.B2 LHC.BPTUV.9L7.B2

References

Status

Assembly Id.LinkLinkComments
CINELHCTCLDA001-CZ000001MTFEDMS
CINELHCTCLDA001-CZ000002MTFEDMS
CINELHCTCLDA001-CZ000003MTFEDMS
CINELHCTCLDA001-CZ000004MTFEDMS
CINELHCTCLDA001-CZ000005MTFEDMS