Main work flow
Start of project
Definition of phased approach
Collimator specifications for phase 1
System layout
(optics, energy
deposition, …)
Radiation,
collimator
shielding
Collimator
mechanical
design
Motors, control
electronics
Budget
Prototyping, verification
with SPS test
Series production
Phase 2 R&D
design, production
OCT02
JUL03
MAY-OCT04
2005-2006
Installation,
commissioning
2006-2007