LHC Collimation Project

Home of the Project for the LHC Collimation System

 
Top Project Team Notes Collimator List Sounds/Movies Meetings
Links Papers Talks (WG) Layout IR3/7 Collimator DB Pictures
MP Tests Sounds 2011        


Beam Tests for LHC Collimators in SPS and TT40

- planning - 
 
Planning: G. Arduini SPS machine
  R. Assmann Collimation project
     
Manpower: Rely on: BLM team
    Collimation team
    Orbit team
    Impedance team
    HOM team
    SPS operation
    US-LARP visitors
    BDI
    CO
       
  Collimation team: 1 hardware person  
    1 accelerator physics person  
  Machine: Gianluigi or Jorg?  
  Orbit team: Jorg or Ralph Steinhagen  
  BLM team Barbara, Lars, hardware person  
  Controls: M. Jonker
  Impedance team: F. Zimmermann, H. Burkhardt, ...
  HOM team: Tom
  Vacuum: Miguel
     
Dates: 11-Oct-2004 MD#1: Beam test in the LHC ring (beam loss response, collimator tuning, set-up with small gaps, impedance)
     
  18-Oct-2004 MD#2: Beam test in the LHC ring (impedance, vacuum, outgassing, higher-order modes, loss maps)
     
  25-Oct-2004 MD#3: Robustness test in TT40
     
Schedule MD1:      
       
Time Beam Activity Persons
       
6 h Low emittance, low intensity (0.9 micron, 3e10, 16 bunches)
  • Commission LHC type BLM's.
  • Measure response function with varying collimator settings.
  • Use of additional collimator to define square beam distribution?
  • Beam stability at 270 GeV.
BLM team
Machine
Collimation team
Orbit team
Controls
       
12 h as above
  • Close collimation gap
  • Center around beam
  • Establish smallest possible gap (goal is 2-3 mm)
Machine
Collimation team
Orbit team
       
6 h Low emittance, highest possible bunch current (tbc)
  • Impedance measurements (different methods)
Machine
Collimation team
Impedance team
BDI (PLL?)
       
Issues Remote control of collimator to be optimized  
  Positioning of BLM's  
  Software control for collimators to be improved (MIDI)  
  Logging of all sensor and collimator information  
  Check of sensor readings and re-calibration if required.  
  Display for BLM data and reception on windows  
  Logging for BLM (collimation team) and orbit data (Orbit team)  
     
       
Schedule MD2:      
       
Time Beam Activity Persons
       
1 h Low emittance, low intensity (0.9 micron, 3e10, 16 bunches)
  • Re-check collimator set-up and position
BLM team
Machine
Collimation team
Orbit team
Controls
       
8 h Low emittance, highest possible bunch current (tbc)
  • Impedance measurements continued (different methods)
Machine
Collimation team
Impedance team
BDI (PLL?)
       
4 h Medium intensity (tbc)
  • Vacuum test with beam loss at shallow angles
Machine
Collimation team
Vacuum group
       
6 h High intensity, 3.5 micron, 270 GeV, possibly 450 GeV
  • Beam loss maps, detailed response of BLM's
  • Response of BPM's with beam loss
Machine
Collimation team
BLM team
Orbit team
       
5 h Reserve    
       
Issues See above    
       
       
Schedule MD3:      
Time Beam Activity Persons
       
8 h 1.1e11, 288 bunches, 450 GeV
  • Send 5 shots for  C-C jaw at 1, 2, 3, 4, 5 mm impact parameter.
  • Send 5 shots for C jaw at 1, 2, 3, 4, 5 mm impact parameter.
Machine
TT40/BT team
Collimation team
BLM team
Vacuum team
       
Issues:   Closure of vacuum valves after each shot?  
    Wait for cool-down of components  
    No fast valve upstream of experiment  
       
       

  RWA, Thursday, 05. April 2012 11:07 +0200